- Consider The Following Precedence Chart Activity Preceding Activities Optimistic Time Days Pessimistic Time Days Mo 1 (63.1 KiB) Viewed 28 times
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) PESSIMISTIC TIME (days) MO
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) PESSIMISTIC TIME (days) MO
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) PESSIMISTIC TIME (days) MOST LIKELY TIME (days) A 5 10 15 B 10 12 14 С 10 10 (10 D 2 4 B,C А 16 12 E 18 14 14 IF 8 12 G A DE IF 10 12 (14 4 8 12 G 2 14 6 The critical path is and minimum project duration is AFI, 32 O AEGJ, 34 BDGJ, 34 O CDG), 30