Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) PESSIMISTIC TIME (days) MO
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) PESSIMISTIC TIME (days) MO
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) PESSIMISTIC TIME (days) MOST LIKELY TIME (days) 10 A 5 |15 B 10 12 14 C 10 10 D B.C 10 4 2 16 E А 4 12 IF 18 8 4 12 А DE F 10 14 12 18 4 G 12 16 2 14 The total slack for activity Cis O 2 ОО 8 4