Question 4 Calculate the amount assigned to each task in the following WBS. [16x 1 = 16 Marks] Total project cost $500.0

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

Question 4 Calculate the amount assigned to each task in the following WBS. [16x 1 = 16 Marks] Total project cost $500.0

Post by answerhappygod »

Question 4 Calculate The Amount Assigned To Each Task In The Following Wbs 16x 1 16 Marks Total Project Cost 500 0 1
Question 4 Calculate The Amount Assigned To Each Task In The Following Wbs 16x 1 16 Marks Total Project Cost 500 0 1 (39.68 KiB) Viewed 34 times
Question 4 Calculate the amount assigned to each task in the following WBS. [16x 1 = 16 Marks] Total project cost $500.000 Design 20% Program 30% Tost 40% Document 5% Produce CD 5% D-1 10% D-2 10% P-1 20% P-2 5% P3 5% Doc-1 2% Doo 2 3% CD-1 5% T: 1 10% T-2 10 T-3 20%