1. With reference to the table below, with a list of activities of a project: Activity Duration (days) Preceding Activit
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
1. With reference to the table below, with a list of activities of a project: Activity Duration (days) Preceding Activit
1. With reference to the table below, with a list of activities of a project: Activity Duration (days) Preceding Activities A 5 B 3 A с 2 A D 2 B,C E 6 B F 1 D G 3 D a. Draw the Activity-on-Node network diagram, including the Early Start, Early Finish, Late Start, Late Finish, Free Slack and Total Slack for each activity. (8 marks) b. Identify the activities that are on the critical path (1.5 marks), and the duration of the project. (0.5 mark).