Given: Daily demand = 50 with a standard deviation of 4, lead time = 2 days, ordering cost = $144 per order, holding cos

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

Given: Daily demand = 50 with a standard deviation of 4, lead time = 2 days, ordering cost = $144 per order, holding cos

Post by answerhappygod »

Given: Daily demand = 50 with a standard deviation of 4, lead
time = 2 days, ordering cost = $144 per order, holding cost = $1
per unit per day, and safety stock of 5 units are required.
Find the optimal order quantity. Choose the closest answer if
needed.
Group of answer choices
80
120
200
100
60