Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

Construction of a building is based on the following network: Activity Predecessors Days A NONE 6 B A 8 C B,A 2 D A 3 E

Post by answerhappygod »

Construction of a building is based on the following
network:
Activity
Predecessors
Days
A
NONE
6
B
A
8
C
B,A
2
D
A
3
E
B
5
F
C,D
5
G
E,F,D
6
1. Draw the project network.
2. Find the critical path
activities.
3. Calculate slack for all
activities.
4. How long will take to complete the
project?