5. The precedence relationships among 12 activities required to perform a project are given in the table below. Activity

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

5. The precedence relationships among 12 activities required to perform a project are given in the table below. Activity

Post by answerhappygod »

5 The Precedence Relationships Among 12 Activities Required To Perform A Project Are Given In The Table Below Activity 1
5 The Precedence Relationships Among 12 Activities Required To Perform A Project Are Given In The Table Below Activity 1 (434.91 KiB) Viewed 37 times
5. The precedence relationships among 12 activities required to perform a project are given in the table below. Activity A B C D E F G H I J KI Duration 32 5 4 6 1 5 3 4 4 5 10 Immediate C,D E,K F F, GG Follower(s) J H, I | H, II J (a) Construct the activity-on-arc network for the relations among the activities in the project. (b) Apply the Critical Path Method (i.e., do the forward and backward calculations) to determine • the minimum time required to complete the project, • the earliest start time, earliest finish time, latest start time and latest finish time, and slack time for each activity, • the early and late event times, • the critical activities, and • the critical path. (c) Based on the results of part (b), draw • the Early Start Schedule, and • the Late Start Schedule for the project. (d) How many days are available for the Activity D and H without delaying the project? (e) Suppose that the indirect cost per day is $250, and we wish to reduce the completion time of the project by time crashing some of the following activities, which can be crashed linearly. Apply heuristic procedure given in the lecture notes to find a feasible solution that minimizes the total crashing cost. Activity (5) Crash Time (days) B 1 D 2 Normal Cost Crash Cost Normal Time (5) (days) 800 600 2 600 300 4 1000 550 5 500 400 3 300 200 5 1000 400 4 G 2 2 H K 3 2 J
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!
Post Reply