An organization is carrying out a project. Construct the network
activity diagram using the following information: Activity
Predecessors Duration (Days) A None 4 B A 4 C A 2 D A 5 E C 2 F B 4
G E 2 H E, F 2 I D 3 J G, H, I 4 a. Using AON notation, carryout
both a forward and backward pass. b. What is the estimated total
duration for the project? c. Identify all paths through the
network. d. Which is the critical path? e. Which activities have
slack time? f. Identify all burst activities and merge
activities.
An organization is carrying out a project. Construct the network activity diagram using the following information: Activ
-