Six trailers are waiting to be unloaded at a docking station. The times required to unload each trailer and the times th
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Six trailers are waiting to be unloaded at a docking station. The times required to unload each trailer and the times th
Six trailers are waiting to be unloaded at a docking station. The times required to unload each trailer and the times that materials they contain are due in the manufacturing are given in this table: Trailer Promised Time (hours) Unloading Time (hours) A 10 6 B 5 4 с 35 15 D 25 18 E 20 10 F 15 12 n mO000 a. Sequence the trailers to minimize the number of tardy containers using Moore algorithm b. Provide the optimal sequence including the six trailers.