Question 2: A construction organization is carrying out several construction projects. One of the project is building a
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Question 2: A construction organization is carrying out several construction projects. One of the project is building a
Question 2: A construction organization is carrying out several construction projects. One of the project is building a house with a unique architecture by 2024. Create Work Breakdown Structure (WBS) for a house construction project. Question 3: An organization is carrying out a project. Construct the network activity diagram using the following information: Activity A Duration (Days) 4 B 4 Predecessors None A A A С с D E F B 2 5 2 4 2 2 3 4 E G H I J E, F D G, H, 1 a. Using AON notation, carryout both a forward and backward pass. b. What is the estimated total duration for the project? c. Identify all paths through the network. d. Which is the critical path? e. Which activities have slack time? f. Identify all burst activities and merge activities.