Q5. There are six jobs, each of which has to go through the machines A and B in the order AB. Processing times in hours
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Q5. There are six jobs, each of which has to go through the machines A and B in the order AB. Processing times in hours
Q5. There are six jobs, each of which has to go through the machines A and B in the order AB. Processing times in hours are given as Job 5 Machine A 7 1 2 3 4 6 3 9 6 10 12 10 Machine B 11 1 8 3 12 Determine a sequence of these jobs that will minimize the total elapsed time