Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

2. The annual mean demand for a certain kitchen-table at Smart Home (SH) is 9,000 units. Ordering cost per order is $50,

Post by answerhappygod »

2. The annual mean demand for a certain kitchen-table at Smart
Home (SH) is 9,000 units. Ordering cost per order is $50, holding
rate is 22%, and unit cost is $500. To apply the EOQ model with
service level, demand records were collected daily. The daily
demand is normally distributed, with a mean of 25 units and a
standard deviation of 15 units. Lead time = 3 days
2.3 SH received an offer from
another supplier to purchase the tables for $498 a unit, but with a
lead time of 60 days. Should this supplier be preferred over the
current supplier (who sells the tables for $500 a unit and requires
only 3 days lead time), if the 92% service level needs to be
maintained? Base your answer merely on the total cost. In the
Answers sheet answer Yes/No, and show the requested quantities.