Consider the following work breakdown structure: Activity А B C D Start Finish Node Node 1 2 1 3 2 4 3 4 Duration (days)
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Consider the following work breakdown structure: Activity А B C D Start Finish Node Node 1 2 1 3 2 4 3 4 Duration (days)
Consider the following work breakdown structure: Activity А B C D Start Finish Node Node 1 2 1 3 2 4 3 4 Duration (days) Optimistic Most Likely Pessimistic 41 50 59 54 60 66 58 70 82 32 41 44 What is the estimated expected (mean) time for project completion? Multiple Choice 41 days O 70 days O 100 days O 120 days O 221 days