The answer should be in CPM method

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

The answer should be in CPM method

Post by answerhappygod »

The answer should be in CPM method
The Answer Should Be In Cpm Method 1
The Answer Should Be In Cpm Method 1 (100.99 KiB) Viewed 48 times
A company have to develop a product has following times schedule Activity Times in weeks Activity Times in weeks 4 8 1 1 1 (1 – 2) (1 - 3) (2-4) (3 – 4) (3-5) (4-9) (5-6) (5 – 7) (6-8) (7-8) (8-9) 2. 1 1 6 8 5 (8 – 10) (9 – 10) 7 4 Construct the network and compute 1. TE and TL for each event 2. Float for each activity 3. Critical path and its duration
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!
Post Reply