Page view A Read aloud II Add text 1) Draw 2. [4 PTS] Consider the following project. What should you do to crash the duration the project by 2 weeks at the minimum possible cost?
Duration Activity (Week) Maximum Crash Cost Reduction (Weeks) Per Week (3) A B 1 2 MOA NON D 2 2 2 1 1 1 2 3,000 2,000 1.000 4.000 5,000 5.000 9.000 10 F G