1. A toy company produces toys using JIT (Just-in-Time).
The daily demand is 60 units. Production lead time is 5 days. The
safety stock is 200 units. The container size is 50 units. How many
kanbans needed?
2. A manufacturing company serves the demand from three
cities. We know the demand for city A is 100, the demand for city B
is 50, and the demand for city C is 80. The coordinates for each
city is below: A (x=10, y=20); B (x=15, y=15); C(x=12, y=18). Using
center of gravity method, please find the optimal location in terms
of the coordinates.