Time left 0:29:02 Consider the following three jobs: uestion 22 ot yet swered Job Due date Workdays remaining arked out of DO A 30 2 2 Flag B 28 3 Jestion C27 5 Currently it is day 25. According to Critical Ratio (ie. CR=time remaining/workdays remaining) technique, which of the three jobs has the highest priority? a. C b. All of them have same priority CB d. A