- The Performance Report Of Bansko Baggage Inice Included The Following Variances For Direct Labor Price Rate 2 050 Un 1 (15.66 KiB) Viewed 82 times
The performance report of Bansko Baggage Inice, included the following variances for direct labor Price (rate) $2,050 un
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
The performance report of Bansko Baggage Inice, included the following variances for direct labor Price (rate) $2,050 un
The performance report of Bansko Baggage Inice, included the following variances for direct labor Price (rate) $2,050 unfavorable Quantity (officiency), 54 400 favorable Also known Units produced 6,500 Actual hours 9,000 Standard cost per direct labor hour: S11 What were the standard direct labor hours allowed for production? ООО O A 6.900 OB 9.186 C. 9,400 OD 6.686