On January 1, 2021, Dreamworld Co. began construction of a new
warehouse. The building was finished and ready for use on September
30, 2022. Expenditures on the project were as follows:
Dreamworld had $5,500,000 in 15% bonds outstanding through both
years.
What was the final cost of Dreamworld's warehouse?
please answer the bold
On January 1, 2021, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on
-