company's policy is to maintain direct materials inventory equal to 30% of the next month's materials requirement. At the end of February the company had 6.180 pounds of direct materials in inventory. The company's production budget reports the following. Production Budget Units to be produced March 3,500 April 5,500 May 5,100 (1) Prepare direct materials budgets for March and April (2) Prepare direct labor budgets for March and April. (3) Prepare factory overhead budgets for March and April. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Prepare direct materials budgets for March and April. ORNAMENTAL SCULPTURES MFG. Direct Materials Budget For the Months of March and April March April Budgeted production (units) 3,500 5.500 Materials requirements per unit (lbs) 8 8 ARAAN
Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Prepare direct materials budgets for March and April. ORNAMENTAL SCULPTURES MFG. Direct Materials Budget For the Months of March and April March April Budgeted production (units) 3,500 5,500 Materials requirements per unit (lbs) 8 8 Materials needed for production (lbs) 28,000 44,000 Budgeted ending inventory (lbs) Total materials requirements (lbs.) 28,000 44,000 Budgeted beginning inventory (lbs) Materials to be purchased (lbs) 28,000 44,000 Direct material cost perib Total budgeted direct materials S $ 0 0
Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Prepare direct labor budgets for March and April. (Round "DL hours required per unit" answers to two decimal places.) ORNAMENTAL SCULPTURES MFG. Direct Labor Budget For the Months of March and April March April Budgeted production (units) DL hours required per unit Total direct labor hours needed 0 Direct labor rate per hour Total budgeted direct labor 0 S 0 $ 0 < Required 1 Required 3 >
Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Prepare factory overhead budgets for March and April. ORNAMENTAL SCULPTURES MFG. Factory Overhead Budget For the Months of March and April March April Total direct labor hours needed VOH rate per DL hour Budgeted variable overhead $ Budgeted fixed overhead Total budgeted factory overhead $ 0 $ 0 $ 0 < Required 2 Required 3
Ornamental Sculptures Mfg. manufactures garden sculptures. Each sculpture requires 8 pounds of direct materials at a cost of $4 per pound and 0.4 direct labor hours at a rate of $19 per hour. Variable manufacturing overhead is charged at a rate of $4 per direct labor hour. Fixed manufacturing overhead is $4,300 per month. The Ornamental Sculptures Mfg. manufactures garden sculptures. Each sculpture requires 8 pounds of direct materials at a cos
-