6. A company makes two products X and Y, using two machines A and B. Each unit of X that is produced requires 50 minutes
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
6. A company makes two products X and Y, using two machines A and B. Each unit of X that is produced requires 50 minutes
company makes two products X and Y, using two machines A and B. Each unit of X that is produced requires 50 minutes processing time on machine A and 30 minutes time on machine B. Each unit of that is produced requires 24 minutes processing time on machine A and 33 minutes time on machine B. Available processing time on machine, A is 40 hours and on machine B is 35 hours. The demand for X in the current week is 35 units and for Y is 5 units. Company policy is to maximize the combined sum of the units of X and the units of Y at the end of the week. Formulate the problem as linear program and solve graphically.
6. A