Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899603
Joined: Mon Aug 02, 2021 8:13 am

Automatic Transmissions, Inc., has the following estimates for its new gear assembly project: price = $1,150 per unit; v

Post by answerhappygod »

Automatic Transmissions, Inc., has the following estimates for
its new gear assembly project: price = $1,150 per unit; variable
cost = $370 per unit; fixed costs = $4.88 million; quantity =
78,000 units. Suppose the company believes all of its estimates are
accurate only to within ±14 percent. What values should the
company use for the four variables given here when it performs its
best-case and worst-case scenario
analysis? (Do not round intermediate
calculations and enter your answers in dollars, not million,
rounded to the nearest whole number, e.g., 1,234,567.)