Question No: 04 This is a subjective question, hence you have to write your answer in the Text Field given below a) "Pro
-
- Site Admin
- Posts: 899603
- Joined: Mon Aug 02, 2021 8:13 am
Question No: 04 This is a subjective question, hence you have to write your answer in the Text Field given below a) "Pro
Question No: 04 This is a subjective question, hence you have to write your answer in the Text Field given below a) "Project Closure is a project in itself Justify the statement b) The following information concerns progress at day 8 of a drug discovery project. Use the 50-50 estimate: Activity Duration (days) Budget (S) Actual cost (S) % completed 1-2 3 300 400 100 1-3 2 400 300 100 2-4 4 600 800 100 3.4 6 800 40 3-5 9 1000 20 4-5 4 500 0 Calculate the cost, schedule and time variances. Also calculate CPI, SPL, CSI, ETC and EAC. Comment on the status of the project [3+6=91