Of the processes listed, which one gives the best finish? Sawing Honing Milling Drilling Turning The following data appl

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

Of the processes listed, which one gives the best finish? Sawing Honing Milling Drilling Turning The following data appl

Post by answerhappygod »

Of the processes listed, which one gives the best finish?
Sawing
Honing
Milling
Drilling
Turning
The following data apply to the machining of a part on an NC
lathe and on an engine lathe:
NC
Lathe Engine
Lathe
Set-up
Time
1.5
Hrs.
1.0 Hr.
Cycle Time
2.0
min.
8.0 min.
Labor
Rate
$23.00/hr.
$20.00/hr.
The following data apply to the machining of a part on an NC
lathe and on an engine lathe:
NC
Lathe Engine
Lathe
Set-up
Time
1.5
Hrs.
1.0 Hr.
Cycle Time
2.0
min.
8.0 min.
Labor
Rate
$23.00/hr.
$20.00/hr.
Machine usage Rate*
$15.00/hr.
$15.00/hr.
Programmer Rate**
$25.00/hr.
N/A
* Our shop charges for machine usage rate during set-up and
operation.
**Assume 1.0 HR programming time for the NC lathe.
What are the VC’s per part for the NC lathe and Engine lathe
respectively?
$15, $15
$38. $35
$1.27, $4.67
$76, $280
Machine usage Rate*
$15.00/hr.
$15.00/hr.
Programmer Rate**
$25.00/hr.
N/A
* Our shop charges for machine usage rate during set-up and
operation.
**Assume 1.0 HR programming time for the NC lathe.
What are the FC’s for the NC lathe and Engine lathe
respectively?
$82, $35
$63, $35
$94.50. $15
$15, $15
The following data apply to the machining of a part on an NC
lathe and on an engine lathe:
NC Lathe Engine
Lathe
Set-up
Time
1.5
Hrs.
1.0 Hr.
Cycle Time
2.0
min.
8.0 min.
Labor
Rate
$23.00/hr.
$20.00/hr.
Machine usage Rate*
$15.00/hr.
$15.00/hr.
Programmer Rate**
$25.00/hr.
N/A
* Our shop charges for machine usage rate during set-up and
operation.
**Assume 1.0 HR programming time for the NC lathe.
At what production quantity are the TC’s for both options
equal?
14
3
47
10
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!
Post Reply