Q2 (a) Produce a Pert Diagram and identify the critical path based on Table Q2(a). Table Q2(a) Description Predecessor A
Q2 (a) Produce a Pert Diagram and identify the critical path based on Table Q2(a). Table Q2(a) Description Predecessor Activity A B с D E F G Planning Analysis Interview Design Database Design Interface Implementation Testing None A B A D C,E F Estimated Time 0.5 4.0 0.5 1.0 0.5 0.5 0.5 (8 marks) (b) Draw a Gantt Chart for 10 weeks by referring to the Extreme Programing project methodology process. (9 marks)