The position of a new point P was measured from the point 1 by using the distance and angular measurements; see the surv

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

The position of a new point P was measured from the point 1 by using the distance and angular measurements; see the surv

Post by answerhappygod »

The position of a new point P was measured from the point 1 by
using the distance and angular measurements; see the survey scheme.
The horizontal position of the points 1 and 2 is given by the
following grid coordinates:
Point 1: N1 = 650 m, E1 = 750
m
Point 2: N2 = 750 m, E2 = 450
m
The angle α= 89o 00’ 00” was measured with the
accuracy characterized by the standard deviation for the angle of
±9”.
The distance d = 1000 m was measured with the accuracy
characterized by the standard deviation of ±5 cm.
The Position Of A New Point P Was Measured From The Point 1 By Using The Distance And Angular Measurements See The Surv 1
The Position Of A New Point P Was Measured From The Point 1 By Using The Distance And Angular Measurements See The Surv 1 (7.88 KiB) Viewed 25 times
1 р.
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!
Post Reply