From the following information, develop an AON project network. Complete the forward and backward pass, compute activity
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
From the following information, develop an AON project network. Complete the forward and backward pass, compute activity
From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take? ID A B Time 4 MOOW Description Survey site Excavate site Install power lines Install drainage Pour foundation Predecessor None А. B B C, D OnM D E 2 3 4 days. The project will take The critical path is The late start on Activity C is The slack on Activity C is The slack on Activity D is The early start on Activity E is days. days. days. days.