3 4 5 8 The partially completed inventory record for the tabletop subassembly in the table below shows gross requirements, scheduled receipts, load time, and current on-hand inventory a. Complete the last three rows of the record for an FOQ of 120 units. (Enter your responses as integers. A response of *O* is equivalent to being not applicable.) Item: M405– Lot Size: Fog - 120 units Description: Tabletop subassembly Lead Time: 2 weeks Week 1 2 6 7 Gross 90 85 85 45 85 requirements Scheduled 120 receipts Projected on hand 45 inventory Planned receipts Planned order releases DOO D LU
b. Complete the last three rows of the record by using the L41. Hot-sizing rule. (Enter your responses as integers. A response of "O* is equivalent to being not applicable.) Item: M405-X Description: Tabletop subassembly Lot Size: L4L Lead Time: 2 weeks Week 5 6 Fod 1 2 3 4 7 8 90 85 85 45 85 120 Gross requirements Scheduled receipts Projected on hand Inventory Planned receipts Planned order releases 45 D D OOO ロロロ
c. Complete the last three rows of the record by using the POQ lot-sizing rule, with P=2. (Enter your responses as integers. A response of "o" is equivalent to being not applicable.) Item: M405-X Lot Size: POQ (P=2) Description: Tabletop subassembly Lead Time: 2 weeks Week 4 5 6 1 2 3 7 8 90 85 85 45 85 120 Gross requirements Scheduled receipts Projected on hand Inventory Planned receipts Planned order releases 45 . ODO D
3 4 5 8 The partially completed inventory record for the tabletop subassembly in the table below shows gross requirement
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
3 4 5 8 The partially completed inventory record for the tabletop subassembly in the table below shows gross requirement
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!