Scenario A. A particular construction
project has the following characteristics:
Task
Duration
Predecessor(s)
A
3
-
B
6
-
C
3
-
D
5
A
E
3
C
F
7
A
G
4
B, D, E
1. Determine the critical path.
2. Determine the expected duration of the project.
Scenario A. A particular construction project has the following characteristics: Task Duration Predecessor(s) A 3 - B 6
-