10. The project described in the following table is scheduled to be completed in 11 weeks. Construct a network diagram using AOA or AON (see Example 5 for either type). Then, answer the follow- ing questions: a. If you were the manager of this project, would you be concerned? Explain. b. If there is a penalty of $5,000 a week for each week the project is late, what is the probability of incurring a penalty of at least $5,000? Path Activity Estimated Time (weeks) Standard Deviation (wks.) P с 4 0.70 птоп D E F 6 3 0.90 0.62 B MO 9 1.90