The time that it takes to do the first job for a worker is 3
hours the worker has a learning percentage of 95%. The worker is
paid $40 per hours. Material cost is $20 per unit. overheads
estimated to be 60% of labor and material cost. He is tasked to do
15 jobs. What is the total estimated cost?
The time that it takes to do the first job for a worker is 3 hours the worker has a learning percentage of 95%. The work
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
The time that it takes to do the first job for a worker is 3 hours the worker has a learning percentage of 95%. The work
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!