A task has an
optimistic completion time of 6 days, a most likely time of 10
days, and a pessimistic time of 14 days. The expected task duration
is:
10.5 days
11.5 days
9.5 days
12 days
11 days
10 days
A task has an optimistic completion time of 6 days, a most likely time of 10 days, and a pessimistic time of 14 days. Th
-