A task has an optimistic completion time of 6 days, a most likely time of 10 days, and a pessimistic time of 14 days. Th

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

A task has an optimistic completion time of 6 days, a most likely time of 10 days, and a pessimistic time of 14 days. Th

Post by answerhappygod »

A Task Has An Optimistic Completion Time Of 6 Days A Most Likely Time Of 10 Days And A Pessimistic Time Of 14 Days Th 1
A Task Has An Optimistic Completion Time Of 6 Days A Most Likely Time Of 10 Days And A Pessimistic Time Of 14 Days Th 1 (64.55 KiB) Viewed 21 times
A task has an optimistic completion time of 6 days, a most likely time of 10 days, and a pessimistic time of 14 days. The expected task duration is: O A. 11.5 days OB. 10 days O C. 10.5 days OD. 12 days O E. 11 days OF. 9.5 days