A task has an optimistic completion time of 6 days, a most likely time of 10 days, and a pessimistic time of 14 days. Th
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
A task has an optimistic completion time of 6 days, a most likely time of 10 days, and a pessimistic time of 14 days. Th
A task has an optimistic completion time of 6 days, a most likely time of 10 days, and a pessimistic time of 14 days. The expected task duration is: O A. 11.5 days OB. 10 days O C. 10.5 days OD. 12 days O E. 11 days OF. 9.5 days