Question 9 A task hus an optimistic completion time of 8 days, a most likely time of 10 days, and a pessimistio time of
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Question 9 A task hus an optimistic completion time of 8 days, a most likely time of 10 days, and a pessimistio time of
Question 9 A task hus an optimistic completion time of 8 days, a most likely time of 10 days, and a pessimistio time of 15 days. The expected task duration ist OA 9.5 days OB. 11 days OC 12 days OD 11.5 days 10.5 days On 10 days
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!