Uc3m Universidad Carlos III de Madrid Department of Business Administration MRP Exercise 1 Bill of materials A (1) Code А. B С Lot 1 1 2 Lead time 1 week 1 week 2 weeks O W B (1) C (2) (the number in parentheses is the number of parts) Build the MRP table taking into account that the final product A required in week 4 is 100 units