1. The following table summarizes the precedence relationships among the activities of a project: Activity Activity Predecessors Days required A 3 B 2 С A 4 D B 5 E B 4 F CD 3 G E 5 a. Construct the network representation for the project (The network should include the earliest time (ET) and latest time (LT) for each network node). b. Identify the project critical path.