a) At a production facility, FAR values are estimated based on data from the previous year. For three working teams A, B
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
a) At a production facility, FAR values are estimated based on data from the previous year. For three working teams A, B
a) At a production facility, FAR values are estimated based on data from the previous year. For three working teams A, B, and C, the observed FAR values are 0.24, 0.12, and 0.12, respectively. > Calculate the overall observed FAR value for the three teams. b) Consider a binary system with four components having the same reliability p. The system is a monotone combined series-parallel system, where each of the components are assumed to be independent. See System 1 diagram below. > Show that the reliability h of this system can be expressed as p³(2-p).