4) “Project” means the longest path in the following questions. a. What is the probability that the project is completed

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

4) “Project” means the longest path in the following questions. a. What is the probability that the project is completed

Post by answerhappygod »

4 Project Means The Longest Path In The Following Questions A What Is The Probability That The Project Is Completed 1
4 Project Means The Longest Path In The Following Questions A What Is The Probability That The Project Is Completed 1 (145.39 KiB) Viewed 31 times
Possible paths Expected Varianc duration S.D e 5.36961 1. A-B-D-E-F-G-H-J-M-P-Q-R-S 52.63 28.83 6 1.46230 2. A-C-D-E-F-G-H-J-M-P-Q-R-S 31.13 2.14 4 5.37106 3. A-B-D-E-F-G-H-I-L-M-P-Q-R-S 54.67 28.85 4 1.46761 4. A-C-D-E-F-G-H-I-L-M-P-Q-R-S 33.17 2.15 3 5.36871 5. A-B-D-E-F-G-H-K-L-M-P-Q-R-S 54.45 28.82 1 1.45897 6. A-C-D-E-F-G-H-K-L-M-P-Q-R-S 32.95 2.13 6 7. A-B-D-E-F-G-H-I-L-N-O-Q-R-S 54.68 28.85 5.37078 1.46657 8. A-C-D-E-F-G-H-I-L-N-O-Q-R-S 33.18 2.15 2 5.36842 9. A-B-D-E-F-G-H-K-L-N-O-Q-R-S 54.47 28.82 6 1.45792 10. A-C-D-E-F-G-H-K-L-N-O-Q-R-S 32.97 2.13 9 For the critical path (A-B-D-E-F-G-H-I-L-M-P-Q-R-S), the different time periods we have obtained are: Most likely time: 52.6 days Optimistic time: 32.6 days Pessimistic time: 85.1 days