Drew Rosen Automation Company estimates the data entry and
verifying times for four jobs as follows:
JOB
DATA ENTRY (HOURS)
VERIFY (HOURS)
A
3.5
2.6
B
2.1
1.2
C
1.8
3.2
D
2.3
1.5
In what order should the jobs be done if the company has one
operator for each job?