Suppose a project's critical path consists of three activities, each with duration estimates as follows ... Duration Est
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Suppose a project's critical path consists of three activities, each with duration estimates as follows ... Duration Est
Suppose a project's critical path consists of three activities, each with duration estimates as follows ... Duration Estimates (days) Activity Optimistic (a) Most Likely (m) Pessimistic (b) X 8 18 29 Y 8 19 Z 5 19 28 What is the standard deviation of this project's expected completion time? (Round to 2 decimal places) 33