Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

A given project activity has the following time estimates: a = 5 b = 34 m = 19 What is the variance ( σ2 ) of this proje

Post by answerhappygod »

A given project activity has the following time estimates:
a = 5
b = 34
m = 19
What is the variance ( σ2 ) of this project activity's
estimated duration? (Round to 2 decimal places)