24. (8 pts) Consider the following data for a project: A B D A A A B - 1 4 3 7 6 What is the expected time that project will be completed? What are the activities on the critical path? What would happen if F now took 4 days Activity Immediate Predecessor Expected Time E F C,D 2 E,F 7 H D 9 G,H 4