The learning curve for a product is 80 percent. The first unit took 100 hours to complete. The manufacturer wants to det
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
The learning curve for a product is 80 percent. The first unit took 100 hours to complete. The manufacturer wants to det
The learning curve for a product is 80 percent. The first unit took 100 hours to complete. The manufacturer wants to determine how many hours the fifth unit will take by using the formula approach. What is the coefficient b for that calculation? Show Excel Computation. -.0969 .80 1.903 -.2231 -.3219