Given a cost estimate in the form: Project Cost = SQi*[Mi+Wi*Li] and all random variables [Q,M,W,L] have a Normal Distri

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

Given a cost estimate in the form: Project Cost = SQi*[Mi+Wi*Li] and all random variables [Q,M,W,L] have a Normal Distri

Post by answerhappygod »

Given a cost estimate in the form:
Project Cost =
SQi*[Mi+Wi*Li]
and all random variables [Q,M,W,L] have a Normal Distribution
-
Variable
Mean
Std. Dev.
Q1
100
10
Q2
50
10
L1
1
1
L2
2
1
W1
20
2
W2
18
1
M1
10
2
M2
20
1
Question 1 – using FOSM fill in this table
Cost Element
Mean
Standard Dev
Labor Unit Rate 1 (W*L)
Labor Unit Rate 2
Labor Cost 1 (W*L*Q)
Labor Cost 2
Material Cost 1 (M*Q)
Material Cost 2
Cost Element 1
Cost Element 2
Total Project Cost
Question 2 - If all of the variables are
“independent” is the final materials cost #1(i.e., Q1*M1)
correlated with the final labor cost #1 (i.e., Q1*L1*W1)?
Question 3 - Is the final material cost #1
correlated with the final material cost #2?