Problem) Estimate the production of a single engine two-axle wheel scraper whose travel time curves are shown in the fig

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

Problem) Estimate the production of a single engine two-axle wheel scraper whose travel time curves are shown in the fig

Post by answerhappygod »

Problem Estimate The Production Of A Single Engine Two Axle Wheel Scraper Whose Travel Time Curves Are Shown In The Fig 1
Problem Estimate The Production Of A Single Engine Two Axle Wheel Scraper Whose Travel Time Curves Are Shown In The Fig 1 (35.59 KiB) Viewed 36 times
Problem Estimate The Production Of A Single Engine Two Axle Wheel Scraper Whose Travel Time Curves Are Shown In The Fig 2
Problem Estimate The Production Of A Single Engine Two Axle Wheel Scraper Whose Travel Time Curves Are Shown In The Fig 2 (42.21 KiB) Viewed 36 times
Problem Estimate The Production Of A Single Engine Two Axle Wheel Scraper Whose Travel Time Curves Are Shown In The Fig 3
Problem Estimate The Production Of A Single Engine Two Axle Wheel Scraper Whose Travel Time Curves Are Shown In The Fig 3 (45.34 KiB) Viewed 36 times
Problem) Estimate the production of a single engine two-axle wheel scraper whose travel time curves are shown in the figures in the previous slides based on the following information. Maximum heaped volume = 31 LCY Maximum payload = 75000 lb - Material: Sandy clay, 3200 lb/BCY and 2650 lb/LCY Rolling resistance 100 lb/ton Job efficiency = 50 min/hr Operating conditions = average Haul road for a single pusher: Section 1. Level loading area Section 2. Down a 4% grade, 2000 ft for hauling Section 3. Level dumping area Section 4. Up a 4% grade, 2000 ft for returning
Scraper Travel Time (Loaded) feet meters 2200 7000 2000 6000 1800 1600 5000 1400 4000 1200 1000 1000-300 3000- 800 200 500 2000 600 100 400 OL 0 0 Note: CAP 6216 .25 .5 .75 DISTANCE ONE WAY 1000 0 200 0 0 5 1 1.5 2 0% 2% 3 25 TIME 3.5 4 4% 4.5 5 6% 8% 10% 12% 14% 16% TOTAL RESISTANCE (Grade plus Rolling) 5.5 minutes
Scraper Travel Time (Empty) feet meters 2200 0% 2% 4% 6% 7000 2000 6000 1800 1600 5000 1400 4000 1200 7 1000 1000 300 3000 800 200 3 500 2000 600 100 400 1000 0 0 200 0 0 0 1.5 2 2.5 Note: CAP 621G 25 .5 .75 DISTANCE ONE WAY 5 1 3 3.5 TIME 4 8% 4.5 5 10% 12% 14% 16% TOTAL RESISTANCE (Grade plus Rolling) 5.5 minutes