Next A company absorb overheads on the basis of machine hours. During the period the budgeted factory overhead was ghc800000 while actual factory overhead stood at ghc840000. The company absorbed ghc780000 overhead with 20000 actual hours of machine. The budgeted level of machine hours for the company is A. 16410hours B. 41026hours C. 20513hours D. 30769hours Reset Selection Save D (31)