How long is the project shown in the diagram below expected to last? с A 0 E B D 2. 4 Activity Expected Time (days) Stan

Posted: Thu Apr 28, 2022 2:33 pm
by answerhappygod
 1
1 (59.66 KiB) Viewed 22 times
How long is the project shown in the diagram below expected to last? с A 0 E B D 2. 4 Activity Expected Time (days) Standard Deviation (days) А 28 3 В 12 2 с 25 3 D 37 4 E 35 2 F 19 1 G 20 2 0 < 65 O >= 65 and < 70 O >= 70 and < 75 O >= 75