Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

4 B P ш п ол I І G

Post by answerhappygod »

 1
1 (32.03 KiB) Viewed 21 times
Activity
Normal Duration (weeks)
Minimum Duration
(weeks)
Normal Cost ($)
Maximum Cost ($)
A
10
8
50,000
62,000
B
5
4
25,000
32,000
C
4
3
20,000
28,000
D
12
8
60,000
90,000
E
15
13
75,000
92,000
F
6
4
30,000
42,000
G
8
5
40,000
62,500
H
7
6
35,000
44,500
LP Formulation
Decision variables
FA = finish time of activity A
FB = finish time for activity B
FC = finish time for activity C
FD = finish time for activity D
FE = finish time for activity E
FF = finish time for activity F
FG = finish time for activity G
FH = finish time for activity H
SA = start time of activity A
SB = start time of activity B
SC = start time of activity C
SD = start time of activity D
SE = start time of activity E
SF = start time of activity F
SG = start time of activity G
SH = start time of activity H
E0 = event time of event 0
= project start time
E1 = event time of event 1
E2 = event time of event 2
E3 = event time of event 3
E4 = event time of event 4
E5 = event time of event 5
E6 = event time of event 6
= desired project completion time
TA = crash time of activity A
TB = crash time of activity B
TC = crash time of activity C
TD = crash time of activity D
TE = crash time of activity E
TF = crash time of activity F
TG = crash time of activity G
TH = crash time of activity H
Note: The crash time for an activity is the amount of time
subtracted from the activity’s normal duration
Parameters
DA = normal duration of activity A
DB = normal duration of activity B
DC = normal duration of activity C
DD = normal duration of activity D
DE = normal duration of activity E
DF = normal duration of activity F
DG = normal duration of activity G
DH = normal duration of activity H
Question 1
What is the shortest possible completion time (in weeks) for
this project?
< 20
>= 20 and < 23
>= 23 and < 26
>= 26 and < 29
> 29
Question 2
How much will this project cost (in $’s)
under normal conditions?
< 300,000
>= 300,000 and < 350,000
>= 350,000 and < 400,000
>= 400,000
Question 3
What would be the total
cost of
activity D if this activity is
completed in 10 weeks?
< 60,000
>= 60,000 and < 70,000
>= 70,000 and < 80,000
>= 80,000
Question 4
What is the cheapest way to reduce the duration of the project
by one week from its normal duration?
Reduce activity A by one week
Reduce activity B by one week
Reduce activity C by one week
Reduce activity D by one week
Reduce activity E by one week
Reduce activity F by one week
Reduce activity G by one week
Reduce activity H by one week
Question 5
Which of the following expressions is the objective for this
crashing problem?
Minimize 6,000 DA + 7,000 DB + 8,000 DC + 7,500 DD + 8,500 DE +
6,000 DF + 7,500 DG + 9,500 DH
Minimize 62,000 TA + 32,000 TB + 28,000 TC + 90,000 TD + 92,000
TE + 42,000 TF + 62,500 TG + 44,500 TH
Minimize 6,000 FA + 7,000 FB + 8,000 FC + 7,500 FD + 8,500 FE +
6,000 FF + 7,500 FG + 9,500 FH
Minimize 6,000 TA + 7,000 TB + 8,000 TC + 7,500 TD + 8,500 TE +
6,000 TF + 7,500 TG + 9,500 TH
Question 6
Which of the following expressions would be included as a
constraint in a linear programming formulation of the crashing
problem for the project?
FB=SB-DB+TB
DE>=0
E3>=FD
TE>=2