Wilton Technologies wishes to use MRP methodology to developing a material requirements plan for the next nine weeks. W

Posted: Thu Apr 28, 2022 2:21 pm
by answerhappygod
Wilton Technologies wishes to use MRP methodology to
developing a material requirements plan for the next nine
weeks. Williston Technologies has gathered the
following information to work with:
Bill of Materials:
Current Inventory
Records:
Inventory
Leadtime Currently
Part (in weeks) Lotsize On-hand
A 1 Lot-for-Lot 50
B 1 75 85
C 2 30 100
D 2 50 415
Master Production Schedule:
-Weeks-
Part 1 2 3 4 5 6 7 8 9
A

0 50 100 100
250
0 200
0
50
Please use MRP methodology to develop a materials requirement
plan for Williston Technologies.
In your plan, in which week is only one of the four parts (A, B,
C and D) being ordered? Which week has only one non-zero
Planned Order Release?
Week 1
Week 3
Week 8
Week 6