Wilton Technologies wishes to use MRP methodology to developing a material requirements plan for the next nine weeks. W

Business, Finance, Economics, Accounting, Operations Management, Computer Science, Electrical Engineering, Mechanical Engineering, Civil Engineering, Chemical Engineering, Algebra, Precalculus, Statistics and Probabilty, Advanced Math, Physics, Chemistry, Biology, Nursing, Psychology, Certifications, Tests, Prep, and more.
Post Reply
answerhappygod
Site Admin
Posts: 899604
Joined: Mon Aug 02, 2021 8:13 am

Wilton Technologies wishes to use MRP methodology to developing a material requirements plan for the next nine weeks. W

Post by answerhappygod »

Wilton Technologies wishes to use MRP methodology to
developing a material requirements plan for the next nine
weeks. Williston Technologies has gathered the
following information to work with:
Bill of Materials:
Current Inventory
Records:
Inventory
Leadtime Currently
Part (in weeks) Lotsize On-hand
A 1 Lot-for-Lot 50
B 1 75 85
C 2 30 100
D 2 50 415
Master Production Schedule:
-Weeks-
Part 1 2 3 4 5 6 7 8 9
A

0 50 100 100
250
0 200
0
50
Please use MRP methodology to develop a materials requirement
plan for Williston Technologies.
Which of the following is true about your plan?
I.
In Week 9, ending inventory of Part A will be 0.
II.
In Week 4, ending inventory of Part B will be 50.
III.
The Week 2 Planned Order Releases for Part C is 250.