Wilton Technologies wishes to use MRP methodology to
developing a material requirements plan for the next nine
weeks. Williston Technologies has gathered the
following information to work with:
Bill of Materials:
Current Inventory
Records:
Inventory
Leadtime Currently
Part (in weeks) Lotsize On-hand
A 1 Lot-for-Lot 50
B 1 75 85
C 2 30 100
D 2 50 415
Master Production Schedule:
-Weeks-
Part 1 2 3 4 5 6 7 8 9
A
0 50 100 100
250
0 200
0
50
Please use MRP methodology to develop a materials requirement
plan for Williston Technologies.
Which of the following is true about your plan?
I.
In Week 9, ending inventory of Part A will be 0.
II.
In Week 4, ending inventory of Part B will be 50.
III.
The Week 2 Planned Order Releases for Part C is 250.
Wilton Technologies wishes to use MRP methodology to developing a material requirements plan for the next nine weeks. W
-
answerhappygod
- Site Admin
- Posts: 899604
- Joined: Mon Aug 02, 2021 8:13 am
Wilton Technologies wishes to use MRP methodology to developing a material requirements plan for the next nine weeks. W
Join a community of subject matter experts. Register for FREE to view solutions, replies, and use search function. Request answer by replying!